Skip to main content
Colorado General AssemblyToggle Main Menu
Agency NameToggle Agency Menu

j_cdc_2017a_2016-12-20t09:02:24z1 Hearing Summary

Date: 12/20/2016

Location: LSB B

Final

Department of Corrections



COMMITTEE ON CAPITAL DEVELOPMENT COMMITTEE


Votes: View--> Action Taken:
<none> <none>











09:21 AM -- Department of Corrections



Scott Lancaster, Physical Plant Manager, Limon Correctional Facility, and Dennis Dunsmoor, Colorado Correctional Industries (CCi), presented the department's FY 2017-18 capital budget requests: Hot Water Loop Replacement, Limon Correctional Facility (Capital Renewal) and Correctional Industries - Miscellaneous Small Projects. Mr. Lancaster described critical issues with the hot water loop system at Limon Correctional Facility, including leaks, temperature swings, and pressure losses. Committee members received pictures of the hot water loop system (Attachment B).



161220 AttachB.pdf161220 AttachB.pdf



09:29 AM



Mr. Lancaster responded to a committee question regarding the cost of a recent repair to the hot water loop system. He also discussed emergency procedures that were put into place during the repair and responded to committee questions regarding potential construction phasing for the project and the critical nature of the project.



09:37 AM



Mr. Dunsmoor discussed the ongoing cash-funded request for CCi miscellaneous small capital projects.








Colorado legislature email addresses ending in @state.co.us are no longer active. Please replace @state.co.us with @coleg.gov for Colorado legislature email addresses.  Details